LinkedIn Microsoft Project Skills Assessment Answers (2023) (2023)

The LinkedIn Skill Assessments feature allows you to demonstrate your knowledge of the skills you've added to your profile. LinkedIn job advertisers may also add competency ratings as part of the application process. This allows job advertisers to more efficiently and accurately validate the critical skills a candidate must have for a job.

Microsoft Project assessment topics include:

  • Introduction and Interface
  • manage projects
  • Output and Reports
  • Project configuration
  • resources
  • scheduling
  • view
  • division of labor structures
  • Working with multiple projects
  • Working with Tasks

Frageformat

multiple selection

Language

English

Index

  • 1 LinkedIn Microsoft Project Skills Assessment-Antworten
    • 1.1 Where can you set a fixed, effort-driven, manually planned duration?
    • 1.2 You want to be able to edit your entered entries in the entry bar that appears below the ribbon and above the standard input table in the Gantt chart view. You recently got a new computer and noticed that the input bar is missing. how do you fix it
    • 1.3 Which of the following statements defines the scope of the project in terms of deliverables and components and provides the framework on which the status of the project is based?
    • 1.4 Which statement is correct if you activate the option Calculate multiple critical paths in the advanced settings of a master project?
    • 1.5 Which view of Microsoft Project is shown in the image below?
    • 1.6 You want to change the planning mode of a project from planning from a start date to planning from an end date. This action changes the default constraint from "As soon as possible" to "As late as possible". What dialog should you use to make this change?
    • 1.7 A project contains many elements. What is used to describe the amount of work required?
    • 1.8 What option is not available on the Report tab on the ribbon?
    • 1.9 You fix a schedule on someone else's computer. The schedule contains 10,000 tasks. If the duration of a task is changed in a task with fixed units, the start and end dates do not change. The revision mark is not displayed and the Gantt chart stick is not updated. What is the cause of this problem?
    • 1.10 You want to understand which tasks are critical and which are not. If you look at the Gantt chart, how are these tasks identified by default?
    • 1.11 You are working on a project with tasks without flexibility. What kind of constraint does not provide flexibility?
    • 1.12 Duration can have different units in a project. Which duration unit is invalid?
    • 1.13 Microsoft Project uses calendars to plan a project. Which project components can be assigned to a calendar?
    • 1.14 You are working on a project file that contains many linked sub-projects. When saving files, what option can you use to immediately save open files, including those that haven't changed?
    • 1.15 A resource is assigned to a task that is scheduled for 2 days. The resource is scheduled at 100% for 8 hours (8h) per day. The resource performs 10 hours of actual work on the first day. How has the peak of this function changed?
    • 1.16 What is another name for a work breakdown structure?
    • 1.17 A report of Earned Value over time has been requested. You choose a visual report from Microsoft Project. What values ​​does this report template compare when run?
    • 1.18 You are preparing a dish consisting of a main course and several side dishes. You want the finishing of the main dish to drive the finishing of the side dishes. The main course starts earlier and takes longer than the side dishes. You must create a main course link for each of the side dishes. What kind of link is appropriate?
    • 1.19 A resource is overloaded in a project. This resource is responsible for two tasks that must be performed simultaneously. The first of these tasks is on the critical path. What solution should you use to fix an over-allocation?
    • 1.20 How do you mark the progress of a task and have that progress reflected in the task summary task?
    • 1.21 You have many tasks in a project file and you want to turn them into milestones. How can you do that?
    • 1.22 A project was delayed by three months. In this project you set deadlines that also have to be pushed back by three months. What function should you use to achieve these two delays?
    • 1.23 How many default base calendars does Microsoft Project set up for a project?
    • 1.24 A task has a fixed duration When the task units are changed, what value for the task does it automatically change?
    • 1.25 You are working with subproject files (the main project file is not open) and you have saved the changes you made. What happens to the master project when it is opened?
    • 1.26 You need to change a resource pool. Which option is not valid when opening the file with the pool?
    • 1.27 Automatically add new views and tables on your computer. Filter. and Groups is selected for global. You use a custom filter that you created on one of your calendars and modify it to better suit your needs. Now you realize that this change is not available in other programs. how do you fix it
    • 1.28 A cost rate table can be used to create a tier for a resource. What is the maximum number of cost rate tables for each resource in a project?
    • 1.29 In a project, a software developer is currently doing two tasks at the same time. The first task takes 5 days; The second task takes all day. It was decided that the developer could take some time to work on the shorter task in the middle of the longer task without impacting the schedule. What's the best way?
    • 1.30 You want to make the timeline display in the Gantt chart more granular. How many levels does the timeline support?
    • 1.31 You have been assigned ownership of a schedule containing approximately 12,000 tasks. You need to know in detail exactly which tasks have a different ASAP constraint. The most effective way to do this is to create a filter that tests for what conditions?
    • 1.32 You are working with two project files. You want the second project to contain some of the same tasks as the first project along with their work assignments. You choose to copy tasks between projects. What is copied along with the task when the basic copy and paste action is performed?
    • 1.33 You are working with a main project that contains sub-projects and you want to see a list of the tasks that a sub-project file depends on. How can you do this in Microsoft Project?
    • 1.34 You want to manage multiple projects with one project designated as the main project. Which ribbon button are you using?
    • 1.35 What is the default view when creating a new blank project in Microsoft Project?
    • 1.36 A project contains multiple linked tasks. What is the name of a task that is controlled or directed by one or more other task(s)?
    • 1.37 You have several Microsoft Project files open. One contains confidential information, so hide this file. What is true about the hidden file?
    • 1.38 In the figure below, what does the Task ID 9 indicator represent?
    • 1.39 You are using Work Breakdown Structure (WBS) codes for an ongoing project. Due to some schedule changes, the quests were moved, which changed the HOS. How to fix PSP codes?
    • 1.40 You manage a construction project plan with key tasks that are interdependent. You have to provide important materials to your team so that they start constructing different buildings. All materials must be inventoried before they are used in the project. Completing the material and inventory delivery task, which will take more time than the different building stages, will lead to the completion of the building stages. You must create a link from the delivery and inventory task to the construction task. What kind of link is appropriate?
    • 1.41 When dividing the work that needs to be done for a project, what is the smallest unit of work?
    • 1.42 A resource's hours have increased over five days on a specific task. The duration hasn't changed and the task is effort-driven. What item can you add to the Task Usage view to see what has changed?
    • 1.43 You change the work breakdown structure (WBS) code for a project. What is the default length for a selected sequence type?
    • 1.44 You are working on a project plan. You need to do two tasks at the same time so your review team can work on both tasks. What kind of link is appropriate?
    • 1.45 Duration can have different units in a project. Which duration unit is invalid?

Where can you set a fixed, effort-driven, manually planned duration?

  • Teamplaner
  • Dialog The project information
  • task form
  • resource sheet

You want to be able to edit your entered entries in the entry bar that appears below the ribbon and above the standard entry table in the Gantt chart view. You recently got a new computer and noticed that the input bar is missing. how do you fix it

  • Use the View tab in the Project Options dialog box to enable the input bar.
  • Change the Gantt chart view to the Gantt monitor view.
  • Use oProgressiveinstructions continuedesign optionsDialog box to activate the input bar.
  • NOSeeTab on the ribbon on whichshared viewgroup, selectdetails.

Which of the following statements defines the scope of the project in terms of deliverables and components and provides the framework on which the status of the project is based?

  • work package
  • worktear offstructure
  • baseline
  • Marco

Which statement is correct when you enable the Calculate multiple critical paths option in the advanced settings of a master project?

  • Critical paths are calculated individually for the sub-projects.
  • Critical paths are calculated for individual features.
  • Critical paths are corrected at milestones.
  • Only one critical path is calculated for a linked project.

Which Microsoft Project view is shown in the image below?

  • network diagram
  • Task Dependency Report
  • Flussdiagramm
  • Gantt chart

You want to change the planning mode of a project from planning from a start date to planning from an end date. This action changes the default constraint from "As soon as possible" to "As late as possible". What dialog should you use to make this change?

  • resource information
  • project information
  • task information
  • change working hours

A project contains many elements. What is used to describe the amount of work required?

  • task links
  • resource sheet
  • worktear offstructure
  • baseline

What option isn't available on the Report tab on the ribbon?

  • new report
  • network diagram
  • youngest
  • custom

You fix a schedule on someone else's computer. The schedule contains 10,000 tasks. If the duration of a task is changed in a task with fixed units, the start and end dates do not change. The revision mark is not displayed and the Gantt chart stick is not updated. What is the cause of this problem?

  • Captured projects are billed as selected summary tasks.
  • Calculate multiple critical paths is not selected.
  • One of the Com add-ins is not selected.
  • Calculate Project After Each Edit is set to Off.

You want to understand which tasks are critical and which are not. If you look at the Gantt chart, how are these tasks identified by default?

  • Critical tasks are shown in red and other tasks are shown in blue.
  • Critical tasks are shown in dark blue and other tasks in light blue.
  • Critical tasks are shown in a report, while the Gantt chart shows all tasks in blue.
  • Critical tasks are marked with an icon and other tasks are marked in blue.

You are working on a project with tasks without flexibility. What kind of constraint does not provide flexibility?

  • must end
  • Don't start before
  • as quickly as possible
  • don't finish before

In a project, the duration can have different units. Which duration unit is invalid?

  • weeks
  • Std.
  • diam
  • bedroom

Microsoft Project uses calendars to plan a project. Which project components can be assigned to a calendar?

  • tasks and work
  • work and units
  • resources and labor
  • tasks and resources

You are working on a project file that contains many linked subprojects. When saving files, what option can you use to immediately save open files, including those that haven't changed?

  • yes to everything
  • Sim
  • Save as
  • Save on computer

A resource is assigned to a task that is scheduled for 2 days. The resource is scheduled at 100% for 8 hours (8h) per day. The resource performs 10 hours of actual work on the first day. How has the peak of this function changed?

  • Changed to 10am.
  • Changed to 6 o'clock.
  • It changed to 125%.
  • Changed to 110%.

What is another name for a work breakdown structure?

  • a task hierarchy
  • a task link
  • a duration of tasks
  • a leveling of tasks

A report of Earned Value over time has been requested. You choose a visual report from Microsoft Project. What values ​​does this report template compare when run?

  • deserved value. plan and actual value
  • Added value and planned value
  • Added value and real costs
  • Planned value and actual cost

You prepare a dish consisting of a main course and several side dishes. You want the finishing of the main dish to drive the finishing of the side dishes. The main course starts earlier and takes longer than the side dishes. You must create a main course link for each of the side dishes. What kind of link is appropriate?

  • From beginning to end (SF)
  • movie a movie (FF)
  • end to beginning (FS)
  • game by game (SS)

A resource is overloaded in a project. This resource is responsible for two tasks that must be performed simultaneously. The first of these tasks is on the critical path. What solution should you use to fix an over-allocation?

  • Use the Gantt reconciliation view to customize the edays field for the second task.
  • Use the task usage indicator to change the contour of the second task to an initial spike.
  • Use the task usage view to change the outline of the second task to a bell.
  • Use the Reconciliation Gantt view to adjust the Days field for the first task.

How do you mark the progress of a task and have that progress reflected in the task summary task?

  • Use oTasktool on the beltTaskSubtask tab.
  • Enter a value in %Completecampo.
  • Use oTasktool on the beltTaskGuide for the summary task.
  • Use oproject informationdialog box.

You have a lot of tasks in a project file and you want to turn them into milestones. How can you do that?

  • Recreate the tasks and define them as summary tasks.
  • Define tasks as collective tasks.
  • Detach resources from the tasks because the resources are not required for the milestone task.
  • Change the task duration to 0.

A project was delayed by three months. In this project you set deadlines that also have to be pushed back by three months. What function should you use to achieve these two delays?

  • NOProjecttab, clickproject information.
  • NOTasktab, clickpostpone task.
  • NOMessagetab, clickcompare projects.
  • NOProjecttab, clickmove project.

How many default base calendars does Microsoft Project configure for a project?

  • cinco
  • three
  • two
  • six

A quest has a fixed duration When the units of the quest are changed, which value of the quest does it automatically change?

  • allocation
  • work
  • Outline
  • effort

You are working with subproject files (the main project file is not open) and you have saved the changes you made. What happens to the master project when it is opened?

  • The main project will not reflect any changes until the sub-project files are also opened.
  • The master project shows an error.
  • The main project displays a message that changes have been made and the sub-project files need to be opened first.
  • The main project reflects the changes made to the sub-project files.

You need to change a resource pool. Which option is not valid when opening the file with the pool?

  • Open as read/write in the new main project file.
  • Open as read/write and allow others to use the pool.
  • Open as read-only and allow others to use the pool.
  • Open with read/write access while preventing others from updating the pool.

Add new views and tables automatically on your computer. Filter. and Groups is selected for global. You use a custom filter that you created on one of your calendars and modify it to better suit your needs. Now you realize that this change is not available in other programs. how do you fix it

  • Make a copy of the modified filter with More Filters.
  • NOdesign optionsClear and reselect dialog boxesAdd new views, tables and filters automatically. and groups in the world.
  • Using the organizer, copy the modified filter from your calendar to global.mpt and replace the filter when prompted.
  • Under Compare Projects, select the appropriate optionstask tableeresource tableListen.

A tiered rate schedule can be created for a resource using rate tables. What is the maximum number of cost rate tables for each resource in a project?

  • cinco
  • dez
  • six
  • two

A project currently has a software developer performing two tasks at the same time. The first task takes 5 days; The second task takes all day. It was decided that the developer could take some time to work on the shorter task in the middle of the longer task without impacting the schedule. What's the best way?

  • Create a link between tasks with dependency.
  • Change the outline of the first task to Double Peak.
  • Add the -1d delay time to the second task.
  • Break up the longer task to accommodate the shorter task.

You want to make the timeline display in the Gantt chart more granular. How many levels does the timeline support?

  • three
  • cinco
  • dez
  • four

You take responsibility for a schedule with about 12,000 tasks. You need to know in detail exactly which tasks have a different ASAP constraint. The most effective way to do this is to create a filter that tests for what conditions?

  • Constraint TypeSummaryRecurring% CompleteActive
    1. is not the same as As soon as possible.
    2. corresponds to yes.
    3rd is equal to No.
    4. is equal to 100%.
    5. corresponds to yes.
  • Constraint TypeSummaryRecurring% CepleteActive
    1st is less than as soon as possible.
    2. is not the same as yes.
    3rd is equal to No.
    4. is equal to 0%.
    5. corresponds to yes.
  • TypeDetailRecurringDurationActive constraint
    1. is greater than as soon as possible.
    2. corresponds to yes.
    3. corresponds to yes.
    4. is equal to 0d.
    5. corresponds to In progress.
  • Constraint TypeSummaryRecurring% CompleteActive
    1. is not the same as As soon as possible.
    2. is not the same as yes.
    3rd is equal to No.
    4. 1 is less than 100%.
    5. corresponds to yes.

You are working with two project files. You want the second project to contain some of the same tasks as the first project along with their work assignments. You choose to copy tasks between projects. What is copied along with the task when the basic copy and paste action is performed?

  • resources
  • baseline
  • calendar
  • worktear offstructure

You are working with a main project that contains sub-projects and you want to see a list of tasks that a sub-project file depends on. How can you do this in Microsoft Project?

  • On the Project tab, click Subproject.
  • NOSeetab, clickgroup by.
  • OneProjectaway. clickLinks between projects.
  • NOSeetab, clickFilter.

You want to manage multiple projects, where one project is called the main project. Which ribbon button are you using?

  • subproject
  • share resources
  • move project
  • Link between projects

What is the default view when creating a new blank project in Microsoft Project?

  • resource sheet
  • task form
  • Gantt chart with timeline
  • Details Gantt

A project contains multiple linked tasks. What is the name of a task that is controlled or directed by one or more other task(s)?

  • superimposed
  • predecessor
  • Call up
  • successor

You have several Microsoft Project files open. One contains confidential information, so hide this file. What is true about the hidden file?

  • Ötoggle windowList the hidden file.
  • Ötoggle windowThe command does not list the hidden file.
  • To view the file, selecttoggle window.
  • To show a hidden file in whichSeetab, clickOrganize windows.

In the image below, what does the Task ID 9 indicator represent?

  • subproject
  • linked file
  • custom field
  • resource pool

You use Work Breakdown Structure (WBS) codes for an ongoing project. Due to some schedule changes, the quests were moved, which changed the HOS. How to fix PSP codes?

  • VonProjectClick on the tab in the ribbonWBS > Define code.
  • VonProjectClick on the tab in the ribbonWBS > Renumber.
  • VonSeeClick on the tab in the ribbonOrganize.
  • VonSeeTab on the ribbon on whichDatagroup, selectgroup by.

You manage a construction project plan with key tasks that depend on each other. You have to provide important materials to your team so that they start constructing different buildings. All materials must be inventoried before they are used in the project. Completing the material and inventory delivery task, which will take more time than the different building stages, will lead to the completion of the building stages. You must create a link from the delivery and inventory task to the construction task. What kind of link is appropriate?

  • movie a movie (FF)
  • game by game (SS)
  • From beginning to end (SF)
  • end to beginning (FS)

When you break down the work that needs to be done on a project, what is the smallest unit of work?

  • work package
  • Length of time
  • worktear offstructure
  • task assignment

A resource's hours on a specific task have increased over five days. The duration hasn't changed and the task is effort-driven. What item can you add to the Task Usage view to see what has changed?

  • Add a column for actual duration.
  • Add a column for level assignments.
  • Add a column for the peak value.
  • Add a column for mapping.

You change the code of the work breakdown structure (WBS). What is the default length for a selected sequence type?

  • any
  • 5
  • 3
  • 1

You are working on a project plan. You need to do two tasks at the same time so your review team can work on both tasks. What kind of link is appropriate?

  • game by game (SS)
  • end to beginning (FS)
  • From beginning to end (SF)
  • movie a movie (FF)

In a project, the duration can have different units. Which duration unit is invalid?

  • weeks
  • Std.
  • diam
  • bedroom

FAQs

Do employers look at LinkedIn skill assessments? ›

Recruiters can look for people who have passed assessments for specific skills as part of their search parameters and filters. Badges appear with prospect profiles in search results lists, helping recruiters prioritize profiles even if they didn't filter by skills assessments.

Does anyone care about LinkedIn skill assessments? ›

Conclusion. LinkedIn Skill Assessments are a great tool for increasing your visibility on the platform. They are a way of showing off your professional skills and expertise to potential employers and clients. They're also good for helping you understand what kind of career path you want to take.

Can people see if you fail a LinkedIn skill quiz? ›

If you don't pass an assessment for a given skill, you'll be able to retake it one more time after three months. And because I know you're wondering – the answer is no – failed tests are not displayed on your profile.

What happens if you fail LinkedIn skill assessment twice? ›

If you fail a test, you have the option to delete your score permanently. Also, if you fail a test, you have to wait 3 months to retest. Those with formal skills training are at an advantage (a little more about that next)

What score do you need to pass LinkedIn assessment? ›

If you score in the top 30% (determined by comparing your score against a curated benchmark), you'll receive a skill badge, which you can opt to display on your profile and in recruiter searches.

How do I pass a skill assessment on LinkedIn? ›

If you score in the 70th percentile or higher, you'll pass the assessment and have the option of displaying a “verified skill” badge on your profile. If you don't pass, you can take the assessment again once you've brushed up your skills.

Is LinkedIn skill assessment badge worth it? ›

The assessment feature is awesome for several reasons:

Just like Upwork's tests, LinkedIn Skill Assessments are only available for completion once in 3 months. That is how platforms make sure that a professional will actually grow expertise without passing the test 10 times in a row.

How many times can I retake LinkedIn skill quiz? ›

If you don't pass, you can retake the exam after brushing up on your skills. Bear in mind, too, that you can only take each exam once every three months. After you complete an evaluation, LinkedIn gives you a summary of your results.

Do employers actually check LinkedIn? ›

According to a recent report from Jobvite, a company that helps businesses find talent, 77 percent of recruiters use LinkedIn to find candidates.

Do people care about LinkedIn Learning certificates? ›

Value of LinkedIn Learning Certificates

They play a good role in your career growth and open doors for more career opportunities. Aside from career advancement, this certificate shows your professional education, skills, and interests, adding value to your professional profile.

Do LinkedIn skills matter? ›

Yes, endorsements matter on LinkedIn especially if you are looking for opportunities in the platform. They can increase your chance of getting discovered through the related skills your LinkedIn profile shows.

References

Top Articles
Latest Posts
Article information

Author: Nicola Considine CPA

Last Updated: 21/01/2024

Views: 6538

Rating: 4.9 / 5 (69 voted)

Reviews: 84% of readers found this page helpful

Author information

Name: Nicola Considine CPA

Birthday: 1993-02-26

Address: 3809 Clinton Inlet, East Aleisha, UT 46318-2392

Phone: +2681424145499

Job: Government Technician